Zodiac Cabin & Structures Support LLC has been fined $1,316,000 for workplace safety and health violations following an explosion at its carbon fiber production plant north of Spokane, Wash.
Seventeen workers were injured in the oven explosion at the Newport, Wash., facility last July.
A nearly six-month investigation by the Department of Labor & Industries (L&I) concluded that the explosion could have been prevented if Zodiac had used required safety interlocks and safeguards to ensure that the curing oven was used safely and as advised in a consulting engineer’s report.
L&I cited the employer for 17 willful violations for knowingly and willfully exposing workers to the risk of serious injuries. The investigation found the company used defective equipment and didn’t ensure safe procedures were used when processing flammable materials in its industrial curing oven. Each violation carries the maximum penalty of $70,000.
Click Link to Access Free PDF Download
“The 5Cs to Taking a Bulletproof Injured Worker Recorded Statement”
“Had this explosion occurred during the day when many more workers were present, there could have been many more injuries and possibly even deaths,” said Anne Soiza, L&I assistant director of the Division of Occupational Safety and Health. “As it is, 17 people were injured and their lives put at risk from an incident that was highly predictable given the operating conditions.”
Company Also Hit with 18 Serious Violations
Along with the willful violations, L&I cited the company for 18 serious violations, all with the maximum penalty of $7,000 because of the high potential for death or permanent serious harm.
Due to the danger of an explosion, specific safety interlock controls and other safety procedures were supposed to be in place before the highly flammable resins were used in the 90-foot drying oven. Those controls were not in place, despite the fact that Zodiac had advice from its contracted consulting engineer detailing the steps needed to ensure safe operation prior to using the flammable uncured resins.
The investigation found that flammable resins had been run through the oven a number of times prior to the explosion. L&I also discovered that 11 days before the incident, the plant was evacuated due to flammable vapors that created a risk of explosion in the same operation.
Author Kori Shafer-Stack, Editor, Amaxx Risk Solutions, Inc. is an expert in post-injury response procedures and part of the Amaxx team helping companies reduce their workers compensation costs by 20% to 50%. www.reduceyourworkerscomp.com. Contact: [email protected].
©2014 Amaxx Risk Solutions, Inc. All rights reserved under International Copyright Law.
WORK COMP CALCULATOR: http://www.LowerWC.com/calculator.php
MODIFIED DUTY CALCULATOR: http://www.LowerWC.com/transitional-duty-cost-calculator.php
WC GROUP: http://www.linkedin.com/groups?homeNewMember=&gid=1922050/
SUBSCRIBE: Workers Comp Resource Center Newsletter