The importance of workplace safety has proven an expensive lesson for a trio of European employers.
Three construction companies have been fined after a worker was crushed by a falling section of conveyor at a plant in Sleaford, England.
The incident happened during construction of the Sleaford Renewable Energy plant on Boston Road inFebruary of 2013 when the 4.5 ton conveyor section overturned during installation.
It trapped Michael Doyle, a 49-year-old employee of Derby-based Shaw Group UK Ltd, who suffered multiple injuries including four cracked vertebrae, broken ribs, a punctured lung and broken ankle. He has not returned to work since.
Lincoln Magistrates’ Court heard in March of this year that Shaw Group UK Ltd had been subcontracted to install a boiler and associated equipment , including a conveyor system to carry large straw bales, by Burmeister and Wain Energy (BWE).
BWE was one of two Danish companies, the other being Burmeister and Wain Scandinavian Contractor (BWSC), that had formed a consortium to design and build the centre, which burns straw and wood to create electricity and also to provide heat for some local authority buildings.
Shaw Group UK Ltd had already lifted three conveyor sections on to a slope leading up to the boiler by craning them on to a platform at the bottom of the slope. Skates were bolted to the front and rear legs which helped keep the section of conveyor on rails as it was dragged up the slope by manual winches set up at the top.
In order to fix the sections of conveyor in place workers needed to remove the skates and used jacks to raise the legs enough to take the skates off and then lower the legs down onto the rail.
This was carried out successfully on the first three sections but as the jacks were released, on the lower legs of the fourth and final section, one side lowered faster than the other and the conveyor swung towards two workers before violently swinging the other way and turning on its side, trapping Mr Doyle, from Fleetwood, Lancashire, underneath.
HSE Investigation Notes Fault
A Health and Safety Executive (HSE) investigation identified safety failings by all three companies.
Shaw Group UK Ltd had produced a risk assessment and a plan for the installation but it did not consider removal of the skates from the legs of the conveyor sections or the manual winching of the load up the slope. The document had been sent to BWE for checking but the company did not pick up on the omission.
The lifting operation using jacks was not carried out safely and none of the three defendants was managing or monitoring the work in a way that would ensure its safety.
The investigation also found that BWSC failed in its responsibility as principal contractor to ensure work was properly assessed and coordinated between the many contractors on site.
Shaw Group UK Ltd, of Stores Road, Derby, was fined a total of $25,573 and ordered to pay costs of $2,520 after pleading guilty to breaching Regulation 3(1) of the Management of Health and Safety at Work Regulations 1999; Regulation 8(1)(c) of the Lifting Operations and Lifting Equipment Regulations 1998; and Regulation 13(2) of the Construction (Design and Management ) Regulations 2007.
Burmeister and Wain Scandinavian Contractor, of Gydevang, Allerød, Denmark, was fined $6,882 and ordered to pay costs of $2, 520 after pleading guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974.
Burmeister and Wain Energy, of Luntoftegardsvej of Lyngby, Denmark, was fined $7, 885 and ordered to pay costs of $2, 520 after admitting a breach of Regulation 13(2) of the Construction (Design and Management) Regulations 2007.
HSE inspector Martin Giles noted,
“This was a large site with multiple contractors and up to 300 people working at any one time. Although there was a series of site rules set out in a construction phase plan, BWSC’s management of the site was poor as each of the main contractors ran their own areas of the site as they desired and were able to set additional rules. This led to different procedures being followed and a lack of control over temporary works.
“The failure to ensure work was carried out safely on the slope was symptomatic of more general failures which were the responsibility of principal contractor BWSC in setting the rules, procedures and checks needed to manage a large site. These failures put all the workers on site at risk.”
Author Kori Shafer-Stack, Editor, Amaxx Risk Solutions, Inc. is an expert in post-injury response procedures and part of the Amaxx team helping companies reduce their workers compensation costs by 20% to 50%. www.reduceyourworkerscomp.com. Contact: [email protected].
©2014 Amaxx Risk Solutions, Inc. All rights reserved under International Copyright Law.
WORK COMP CALCULATOR: http://www.LowerWC.com/calculator.php
MODIFIED DUTY CALCULATOR: http://www.LowerWC.com/transitional-duty-cost-calculator.php
WC GROUP: http://www.linkedin.com/groups?homeNewMember=&gid=1922050/
SUBSCRIBE: Workers Comp Resource Center Newsletter